Exclusive: Rutherford County Legal Department redacts records, took 41 days to release $85k jail change order

Commissioners voted Nov. 2 to use money already set aside for unexpected construction costs. The contractor’s October schedule lists Sept. 28, 2027, for completion.
Rutherford County commissioners voted Nov. 2 to cover $85,791 in added jail renovation costs after crews uncovered loose and broken bricks inside roof supports. A public records request about the project was already with the county’s Legal Department. WCAB News received the contractor’s unsigned change order 22 days after the vote and 41 days after filing the request.
WCAB News filed the public records request on Oct. 14, asking about construction progress, delays, the completion date, and funding after this reporter saw what appeared to be a work stoppage on Oct. 13. The county’s records portal shows the request went to the Legal Department that day, and staff acknowledged it the same afternoon.
Vannoy Construction prepared the change order Oct. 23. The portal shows no interim update before staff posted one 15-page PDF on Nov. 24, marked the request fulfilled, and closed it.
North Carolina law requires agencies to provide copies of public records “as promptly as possible” and sets no fixed deadline. The county cited a public security exemption to redact a site plan. The same statute expressly makes budget information on public building construction and repairs a public record.
What the $85,791 covers
Moseley Architects said in an Oct. 20 letter that a demolition crew exposed the damaged masonry piers Sept. 30. The piers support the roof’s steel beams. A structural engineer visited to help stabilize the area, and the engineering team issued revised drawings so work could continue.
The largest charge was $39,326 for staffing and office rental tied to the 23-working-day extension. Vannoy also listed $26,290 for temporary supports and demolition, $7,004 for new masonry piers and $7,500 for engineering and revised drawings.
The change order would raise the construction contract from $8,511,011 to $8,596,802.
Commissioners voted to cover the increase with money already budgeted for the project. County budget records identify a $10 million state appropriation for jail renovations.
Vannoy’s Oct. 23 schedule lists Aug. 3, 2027, for the county to start using the addition and Sept. 28, 2027, for construction to finish.
Sheriff Aaron Ellenburg told WCAB’s The Floor Is Yours that the renovation would add a new intake area, holding cells, and space for people with medical needs. He estimated the county spent nearly $500,000 housing inmates elsewhere in fiscal 2025-26 because of overcrowding. Commissioners set aside an additional $400,000 in April to cover projected out-of-county housing costs.
Commissioners approved the initial proposal in 2024. Jail renovations were discussed publicly dating back to at least 2012, according to public records uncovered by WCAB News.
Three new commissioners are set to take office on December 7; they will join the two commissioners who were seated after the 2024 election, after the initial jail funding vote.